馃攳
How to Work with Accrual Costs in Microsoft Project 2016 - YouTube
Channel: Simon Sez IT
[8]
Welcome back to our course on Project 2016
Advanced.
[13]
In this section I鈥檓 going to take a look
at Cost Accrual.
[17]
This may well be something that you鈥檙e very
familiar with if you鈥檝e been using Project
[21]
for a while, but for some people who perhaps
aren鈥檛 very familiar with accounting practices
[28]
Cost Accrual can seem a little bit of a mystery.
[31]
So what I鈥檝e done for this section is to
create a sort of dummy project.
[34]
It鈥檚 just got five tasks in it and I鈥檝e
also created a few resources as well.
[40]
The resources have different accrual methods.
[44]
So resources 1 to 3 are prorated, resource
4 accrues at the start, resource 5 accrues
[51]
at the end.
[52]
Now when a cost accrues that鈥檚 basically
the point in time at which the accounting
[59]
function associated with a project recognizes
that the cost has been incurred.
[65]
And although generally speaking people recognize
how cost accrual works, for example in terms
[72]
of labor costs.
[73]
So you would normally prorate labor costs
over the course of the task in which the labor
[78]
is employed.
[80]
There are exceptions.
[82]
And with some of the less usual costs associated
with a project it鈥檚 important to recognize
[88]
exactly when the accrual will occur, particularly
as some of the costs might be quite large
[94]
figures.
[95]
So it鈥檚 not possible for me or indeed anybody
else to say costs are always accrued in this
[100]
way or that way.
[102]
But what it is important to understand is
how cost accrual actually works with Project
[108]
2016.
[110]
So when you enter a task or a resource or
you set up a resource assignment it鈥檚 important
[115]
to understand the consequences of the accrual
method that applies in that case.
[121]
Now at the moment as you can see I have no
costs incurred at all on this project.
[127]
In fact there are no costs associated with
the project.
[129]
I haven鈥檛 assigned any fixed costs or resources
to it.
[133]
So the first thing I鈥檓 going to do is to
assign a fixed cost for Task A. And the fixed
[140]
cost for Task A is going to be $100.
[145]
And the accrual method for that is going to
be at the start.
[152]
Now notice that the actual is still zero.
[157]
Now for Task B I鈥檓 also going to have a
fixed cost.
[161]
That鈥檚 also going to $100 and that is going
to be prorated.
[168]
Now what I鈥檓 going to do is to go to the
Project tab and set the status date on this
[175]
project to today.
[177]
So that鈥檚 Monday, July 4th.
[180]
And I鈥檓 going to click on Update Project
and update the project to say that the work
[186]
is complete up to today according to schedule
for the entire project and then I鈥檓 going
[193]
to click on OK.
[196]
Now what you鈥檒l see is that Task A is now
in effect 20% complete.
[202]
So one-fifth of the work is done.
[205]
But the actual cost there of course is the
full amount of the fixed cost, which is accrued
[212]
at the start of Task A. So the actual cost
for Task A is currently $100.
[218]
The remaining cost is $0.
[221]
And basically what happens with a cost that
is accrued at the start is that as soon as
[227]
the task has an actual start date, so as soon
as you record any progress which causes an
[234]
actual start date to be recorded then that
cost is accrued, all of that cost is accrued.
[241]
For Task B, however, where the fixed cost
is prorated we鈥檝e done one-tenth of the
[248]
task, one-tenth of the duration of the task
is complete and so we have incurred one-tenth
[254]
of the fixed cost.
[256]
So the actual is $10 and the remaining is
$90.
[260]
So now what I鈥檓 going to do is to go through
each of the five tasks and assign one of the
[267]
resources to each of the tasks.
[269]
So Resource 1 to Task A, Resource 2 to Task
B and so on.
[274]
So just join me again when I鈥檝e done that.
[278]
So having made those assignments you can see
the effects on the cost.
[281]
For Task A, for example, of course we鈥檝e
incurred the whole of the fixed cost for Task
[289]
A which was accrued at the start.
[293]
But now we also have eight hours work at $50
an hour for Resource 1 whose cost is accrued
[302]
prorate throughout the project.
[304]
For Task B we鈥檝e accrued just one-tenth
of the fixed cost.
[308]
So that鈥檚 $10.
[310]
But we鈥檝e had eighty hours work from Resource
2 and Resource 2鈥檚 eighty hours at $60 an
[318]
hour, that鈥檚 $4,800, etcetera.
[321]
Task D we have an actual cost of $100.
[326]
Bear in mind that the Resource 4 that鈥檚
assigned there doesn鈥檛 have an hourly rate.
[332]
Only has a cost per use and that is accrued
at the start, whereas for Task E, Resource
[340]
5 also doesn鈥檛 have an hourly rate.
[342]
It has a cost per use.
[344]
But this is accrued at the end.
[347]
So there is no actual cost so far.
[350]
So it鈥檚 important to understand how this
accrual works.
[353]
I鈥檒l just make one other change.
[354]
I have one other point to make here if you
like.
[357]
If I go back to the Resource Sheet again and
change Resource 2 so that the cost is accrued
[368]
at the start, to the sheet, and you will see
the cost that鈥檚 already accrued for Task
[376]
B is a pretty large amount.
[379]
So we鈥檙e talking about 80 hours at $60 an
hour.
[384]
That鈥檚 $4,800.
[385]
And then we have $10, which is one-tenth of
the fixed task cost.
[391]
The fixed task cost of course accrued prorate.
[395]
So basically that鈥檚 how accrual works.
[398]
But let me just finish this section by referring
you to Project Options, the Schedule page.
[404]
Right at the bottom there there is an option,
the Default Fixed Cost Accrual method.
[410]
The default Default is prorated.
[412]
You can of course change it to one of those
others.
[415]
And just above that another setting that you
may not be familiar with, actual costs are
[420]
always calculated by project.
[423]
Some people prefer to do all of the work on
actual costs themselves.
[428]
So they uncheck this box and then they calculate
actual costs rather than let Project use the
[434]
sort of methods you鈥檝e seen in this section
to calculate actual costs as you go along.
[440]
So that鈥檚 an option.
[441]
I cannot ever remember unchecking myself but
it may suit you in some situations to do so.
[446]
That鈥檚 it on accrual.
[449]
In the next section we鈥檙e going to look
at Budget Costs.
[453]
So please join me for that.
Most Recent Videos:
You can go back to the homepage right here: Homepage