馃攳
(17 of 20) Ch.9 - IRR vs NPV approach when comparing 2 projects - YouTube
Channel: unknown
[0]
Next example, A and B, two projects, are mutually
exclusive.
[7]
Which project should you accept and why?
[11]
What do we know for each project?
[13]
Project A would require spending $400 in year
zero.
[18]
In year one, it will return $325, in year
two, it will return $200.
[25]
We also know that the internal rate of return
for project A is 22.17% which is also something
[33]
you can calculate yourself.
[36]
And at 10% discount rate, the net present
value is $60.74.
[43]
For project B, cash flow zero is negative
500, cash flow in year one is 325, cash flow
[51]
in year two is 325 again, the IRR is 19.43%
and the net present value at 10% discount
[61]
rate is $64.05.
[65]
So, the question again is which project should
you accept and why?
[73]
Because A and B are mutually exclusive, it
means we can only pick one project if both
[80]
look acceptable, right?
[82]
Now, we are given the IRR and we are given
the net present value for each.
[89]
So, let's see which project would be picked
based on the IRR criteria.
[96]
So based on the IRR rule, you can see that
the IRR is higher for project A than for project
[108]
B, right, 22.17% is larger than 19.43%.
[114]
And so, for this reason, you can say that
we make a higher return on our money, right,
[122]
for every dollar invested, right, for project
A. And because in both cases you make a better
[131]
return than what's typical, which is 10% per
year, technically both are good projects but
[138]
because they are mutually exclusive, we need
to pick the one that's better and that's project
[144]
A. You can also say that project A is the
winner because it has a wider range of acceptable
[150]
required returns.
[152]
Now, let's look at which one we would choose
based on the net present value rule.
[158]
So, both net present values are above zero,
making both projects acceptable except we
[166]
need to pick one because they are mutually
exclusive.
[170]
So, which one is better?
[173]
The one with a higher net present value is
better, and that's project B, right?
[179]
Project B will generate an overall profit
of $64.5 and project A will only generate
[186]
a profit of $60.74.
[190]
So based on the IRR rule, project A is the
winner.
[195]
Based on the NPV rule, project B is the winner.
[199]
So, what do we do?
[203]
The two approaches sort of contradict each
other, right, when we are applying them to
[207]
comparing to competing projects.
[211]
And in this case, you should always go with
the net present value approach, with the recommendation
[218]
that the net present value technique provides.
[223]
And this was also the case on the earlier
slides in this chapter when we would try using
[231]
the net present value approach and one more
approach, let's say, the profitability index
[237]
approach or the payback period approach.
[240]
And in all those cases, we would always conclude
that when in doubt, when there is a conflict
[247]
between the NPV approach and one other approach,
then always go with the NPV approach.
[255]
Why?
[256]
Because that's the approach that tells you
exactly how much cash you will get as a profit.
[263]
So, to conclude this [inaudible] for example,
project B with a higher NPV should be the
[272]
winner.
[273]
Now, let's look at the same exact problem
but we are only changing the wording slightly.
[281]
A and B are no longer mutually exclusive,
they are now independent.
[287]
What does independence mean?
[289]
It means if both projects happen to be acceptable,
we will accept them both.
[297]
Again, let's make our decision based on the
IRR criteria.
[301]
The IRR rule says a project should be accepted
if the required return, which is 10% in this
[310]
problem, is less than the IRR and both IRRs
are above 10%, which makes both projects A
[319]
and B acceptable.
[322]
And because they are independent, we are independently
making our decision regarding each project.
[328]
So, we are going to choose them both, both
A and B. Now, the net present value rule,
[335]
what does the rule say?
[337]
A project should be accepted if the net present
value is above zero dollars, right?
[342]
Is it?
[343]
Yes, $60.74 for project A, that's above zero
dollars, and for project B, the NPV is $64.05,
[352]
again, a positive number.
[355]
So once again, if we make our decision on
each project independently, we would be accepting
[362]
both A and B. So here, we didn't have any
sort of contradiction between the two approaches.
[370]
They agree and it's going to be a clear decision
to make.
[375]
We're going to accept both projects in this
situation.
Most Recent Videos:
You can go back to the homepage right here: Homepage





