Is the COVID-19 Pandemic a Force Majeure Event? - YouTube

Channel: unknown

[0]
In December of 2019 a new corona virus was discovered in Wuhan China. In the
[5]
weeks and months to follow it spread around the globe bringing with it
[10]
illness and triggering dramatic government responses now with global
[15]
business disrupted we'll take a look at if and one the corona virus may trigger
[21]
a provision known as force majeure or act of God hello and welcome to talks on
[27]
law i'm Joel Cohen and we are joined remotely by Jose Moran a partner at
[32]
Baker McKensie where he leads that firms energy, infrastructure, and mining
[37]
practice group, Jose, welcome and before we get started on the corona virus maybe
[42]
you could lay some foundation what is a force majeure provision the term force
[47]
majeure also reflect referred to as an act of God addresses scenario when
[51]
performing contract obligations becomes impossible difficult or onerous to
[57]
perform due to exceptional events outside of either's parties control with
[63]
that background how do you apply the analysis of kovat 19 or the government
[69]
shutdowns to force majeure provision generally there are two approaches for
[74]
contracts governed by common law the first approach is to have an open or non
[79]
exhaustive list of events or clauses include a list of example events force
[85]
majeure events that we have seen expressly listed may apply to Kabat 19
[90]
such as an epidemic or pandemic a government action or indirect or
[95]
intervention a quarantine a shortage of labor or materials if there's one
[102]
takeaway from the recent events particularly light of the very narrow
[105]
construction that courts have applied in certain jurisdictions is to a pandemic
[111]
an or epidemic language to future force majeure clauses now sometimes these
[117]
lists are open-ended and leave open the possibility of events unforeseen by the
[123]
drafters how are courts interpreting that parties must be very careful
[129]
placing too much reliance on a catch-all language
[132]
and sort of an open list for example New York courts a New York law construes
[137]
force majeure provisions very narrowly and a New York court typically will find
[142]
an event to be covered by a catch-all only if it's of the same nature and kind
[148]
and those as those events that are specifically listed you mentioned there
[152]
are two types of force majeure provisions we talked about one
[157]
what's the second approach the second approach is to have a general objective
[161]
test for example an event beyond control of the parties an event that could don't
[166]
recently have been provided against or that could not recently have been
[170]
avoided or an event that is not attributable to either party now
[175]
regardless of the type of force majeure provision or the drafting are their
[180]
duties or obligations of a party even where the force majeure provision may be
[186]
triggered the affected party cannot generally just sit on its hands there's
[192]
often an obligation on the affected party to mitigate the effects of a force
[197]
majeure event for example sourcing alternative supply or labor even if that
[202]
is more expensive or moving personnel to avoid restrictions we perhaps between
[207]
two operating projects plants or assets at the very least there's an obligation
[212]
to mitigate and it will require talking to the other party to the agreement and
[216]
trying to make alternative arrangements and perhaps creating an amendment to the
[221]
agreement or what its so called a reopener a follow-up question Jose
[225]
sometimes these force majeure provisions have exceptions or carve outs what are
[230]
you seeing in the market there's almost always a list of exclusions an
[235]
obligation to pay money is perhaps the most frequently seen but matters such as
[240]
economic hardship reductions in demand and sorta gist of labor are commonly
[246]
seen particularly in projects in developed countries these exclusions can
[251]
be extremely important as they can completely negate otherwise valid claims
[255]
and for existing projects they are not always negotiated as fully and as
[260]
carefully as they should and lastly before we let you go if the force
[265]
majeure provision is triggered what are some of the
[268]
remedies that the parties may have generally an excuse against known
[273]
performance to the extent that the force majeure event affects performance the
[277]
affected party has no liability for non performance often an express right of
[282]
suspension and lastly termination of the contract for prolonged force majeure
[288]
periods Thank You Jose Moran for your time and for those that are watching
[293]
remember this is a global issue so each individual case will depend on the
[300]
circumstances of that case the law governing in that state or country and
[304]
the specific drafting of the governing contract i'm joel coen thanks for
[309]
watching talks on law
[315]
you