馃攳
Is the COVID-19 Pandemic a Force Majeure Event? - YouTube
Channel: unknown
[0]
In December of 2019 a new corona virus
was discovered in Wuhan China. In the
[5]
weeks and months to follow it spread
around the globe bringing with it
[10]
illness and triggering dramatic
government responses now with global
[15]
business disrupted we'll take a look at
if and one the corona virus may trigger
[21]
a provision known as force majeure or
act of God hello and welcome to talks on
[27]
law i'm Joel Cohen and we are joined
remotely by Jose Moran a partner at
[32]
Baker McKensie where he leads that
firms energy, infrastructure, and mining
[37]
practice group, Jose, welcome and before
we get started on the corona virus maybe
[42]
you could lay some foundation what is a
force majeure provision the term force
[47]
majeure also reflect referred to as an
act of God addresses scenario when
[51]
performing contract obligations becomes
impossible difficult or onerous to
[57]
perform due to exceptional events
outside of either's parties control with
[63]
that background how do you apply the
analysis of kovat 19 or the government
[69]
shutdowns to force majeure provision
generally there are two approaches for
[74]
contracts governed by common law the
first approach is to have an open or non
[79]
exhaustive list of events or clauses
include a list of example events force
[85]
majeure events that we have seen
expressly listed may apply to Kabat 19
[90]
such as an epidemic or pandemic a
government action or indirect or
[95]
intervention a quarantine a shortage of
labor or materials if there's one
[102]
takeaway from the recent events
particularly light of the very narrow
[105]
construction that courts have applied in
certain jurisdictions is to a pandemic
[111]
an or epidemic language to future force
majeure clauses now sometimes these
[117]
lists are open-ended and leave open the
possibility of events unforeseen by the
[123]
drafters how are courts interpreting
that parties must be very careful
[129]
placing too much reliance on a catch-all
language
[132]
and sort of an open list for example New
York courts a New York law construes
[137]
force majeure provisions very narrowly
and a New York court typically will find
[142]
an event to be covered by a catch-all
only if it's of the same nature and kind
[148]
and those as those events that are
specifically listed you mentioned there
[152]
are two types of force majeure
provisions we talked about one
[157]
what's the second approach the second
approach is to have a general objective
[161]
test for example an event beyond control
of the parties an event that could don't
[166]
recently have been provided against or
that could not recently have been
[170]
avoided or an event that is not
attributable to either party now
[175]
regardless of the type of force majeure
provision or the drafting are their
[180]
duties or obligations of a party even
where the force majeure provision may be
[186]
triggered the affected party cannot
generally just sit on its hands there's
[192]
often an obligation on the affected
party to mitigate the effects of a force
[197]
majeure event for example sourcing
alternative supply or labor even if that
[202]
is more expensive or moving personnel to
avoid restrictions we perhaps between
[207]
two operating projects plants or assets
at the very least there's an obligation
[212]
to mitigate and it will require talking
to the other party to the agreement and
[216]
trying to make alternative arrangements
and perhaps creating an amendment to the
[221]
agreement or what its so called a
reopener a follow-up question Jose
[225]
sometimes these force majeure provisions
have exceptions or carve outs what are
[230]
you seeing in the market there's almost
always a list of exclusions an
[235]
obligation to pay money is perhaps the
most frequently seen but matters such as
[240]
economic hardship reductions in demand
and sorta gist of labor are commonly
[246]
seen particularly in projects in
developed countries these exclusions can
[251]
be extremely important as they can
completely negate otherwise valid claims
[255]
and for existing projects they are not
always negotiated as fully and as
[260]
carefully as they should and lastly
before we let you go if the force
[265]
majeure provision
is triggered what are some of the
[268]
remedies that the parties may have
generally an excuse against known
[273]
performance to the extent that the force
majeure event affects performance the
[277]
affected party has no liability for non
performance often an express right of
[282]
suspension and lastly termination of the
contract for prolonged force majeure
[288]
periods Thank You Jose Moran for your
time and for those that are watching
[293]
remember this is a global issue so each
individual case will depend on the
[300]
circumstances of that case the law
governing in that state or country and
[304]
the specific drafting of the governing
contract i'm joel coen thanks for
[309]
watching talks on law
[315]
you
Most Recent Videos:
You can go back to the homepage right here: Homepage





