Illustrative examples for evaluation of bids based on different schemes - YouTube

Channel: unknown

[0]
[Music]
[10]
[Music]
[13]
namaskar and welcome to this module on
[16]
principles of construction management
[18]
and this is lecture number four in this
[21]
module and we will do
[23]
illustrative examples for evaluation of
[25]
bids
[26]
based on different schemes
[29]
so now to start the discussion
[32]
let us consider a project whose
[33]
estimated cost is let us say
[36]
rupees 100 000
[37]
and the details of the financial bids
[39]
submitted by four bidders
[42]
is as follows
[44]
we have bidders a b c and d
[46]
and they bid 95 87 64 and 76 000 rupees
[52]
now if the rules of the game were to be
[55]
that award to the lowest bidder that is
[58]
the simplest of rules that is the so
[60]
called
[61]
l one criteria
[63]
there is no discussion
[65]
sixty four is the lowest
[67]
the bidder is c
[69]
the project is awarded to bidder c
[73]
now the situation need not be all that
[74]
simple
[76]
if we now consider a situation
[80]
where for the same project let us say
[81]
about 100 000 rupees
[84]
the details of technical bids and their
[86]
financial bids are available to us
[89]
what we are saying is
[91]
that there is
[93]
a technical bid
[95]
and based on
[96]
some criteria
[98]
we are not getting into that criteria
[100]
and this evaluation here in this
[102]
lecture but at some point of time
[104]
perhaps we will
[105]
let us say that we have been able to
[107]
evaluate the four bidders at 80 75 45
[112]
and 60
[113]
out of 100
[115]
and the financial bid given by these
[118]
bidders is
[119]
this
[120]
now what could be the options
[123]
the options could be
[124]
that the bid should be evaluated in a
[126]
manner
[127]
that the technical score must be more
[130]
than 50.
[131]
so basically what we are saying is that
[134]
a person or a bidder should have at
[137]
least 50 points
[139]
out of 100
[141]
in the technical score
[144]
and for only technically qualified
[146]
bidders cost will be the only criteria
[149]
to select the contractor
[151]
now if this was the rule
[153]
then
[154]
bidder c gets disqualified
[157]
because this number
[159]
is less than fifty so this goes out of
[162]
the consideration all together
[164]
and among those that survive that is a b
[168]
and d
[169]
we can arrange them
[170]
in the order of
[172]
cost
[173]
and we find that b is the lowest
[176]
followed by
[178]
d
[178]
and
[179]
followed by a
[181]
so in this case
[182]
the decision is again
[184]
simple
[186]
b is awarded the job
[188]
so what we have done here
[190]
is said that
[191]
there is a threshold technical score
[194]
beyond which
[196]
everybody is equal so we are not trying
[198]
to differentiate between
[200]
d which scored 60 points and a which
[204]
scored 80 points on the technical bit
[206]
now if we want incorporate this
[209]
we will have to
[211]
give a weightage to the technical scores
[214]
and the financial scores so that is what
[216]
is done here in an alternative scenario
[218]
where we say that the technical score
[219]
must be more than 50 which is the same
[221]
condition as
[222]
the last one
[224]
and we have said that the job is awarded
[226]
to the bidder with the highest
[228]
composite score
[231]
evaluated by considering
[233]
equal weightage to technical and
[236]
financial bids it is easier said than
[238]
done
[239]
because
[240]
what we have is information like this of
[244]
course
[244]
without getting into the details as to
[246]
how these
[247]
points or marks were arrived at we have
[250]
an even bigger problem of converting
[253]
this
[254]
to some kind of marks
[257]
how do we convert the quoted prices
[260]
which is the financial bids
[262]
into marks so that we can arrive at a
[265]
composite score now one alternative or a
[269]
possibility could be
[270]
that award hundred marks to the lowest
[273]
bidder
[274]
and
[275]
relative to that allocate marks to the
[278]
others proportionately
[280]
if we do that exercise of course
[282]
c gets eliminated in the first round
[284]
because of
[286]
this 45 being less than 50. as far as
[288]
the others are concerned
[290]
b
[291]
which is the
[293]
lowest bid financially is awarded 100
[296]
points
[297]
and
[298]
for a
[300]
this score is 87.76
[303]
arrived at by saying that ok this was
[305]
110 this was the lowest bidder and
[309]
with this
[310]
simple
[311]
linear equation we get
[313]
87.76 and similarly we can get
[316]
97.96 marks for d
[319]
so if we do that
[321]
then what we have is
[324]
this is our technical score and this is
[326]
our financial score we can calculate the
[329]
composite score by giving an equal
[331]
weightage to these and we get these
[334]
numbers
[335]
remember that in this case we have used
[338]
a 50 50 criteria that is the technical
[341]
bid and the financial bid are equally
[343]
weighted now if this happens
[346]
then the highest composite score is
[350]
87.5 and with this score bidder b
[355]
wins the bit
[356]
now of course there is no sacrosanct
[359]
reason why the weightage of the
[361]
technical bid and the financial bid
[363]
should be fifty fifty there can always
[365]
be a situation
[367]
where the weightage is 80 percent to
[369]
technical and 20 percent to the
[372]
financial
[373]
now if that kind of a scenario is
[374]
operated
[376]
then the composite score which is
[377]
calculated becomes something like this
[380]
and
[381]
here
[383]
bidder a
[385]
becomes the winner of the project
[389]
so it is obvious that if we increase the
[391]
weightage of the technical bid
[394]
bidder d
[397]
which scored the lowest as far as the
[399]
technical bid is concerned
[400]
gets more and more disadvantaged
[403]
and bidder a which is
[406]
the technically most sound
[409]
becomes in an advantageous position
[412]
in this example
[413]
if we consider the technical and
[415]
financial bids of four bidders
[417]
as given here in this table
[421]
and these marks being evaluated out of
[424]
hundred based on some criteria
[427]
the rules of the game being the
[428]
following
[429]
there is case one technical marks are
[432]
not considered
[433]
job will be awarded to the lowest bidder
[435]
that was the simplest case that we
[437]
discussed right in the beginning of this
[439]
discussion
[440]
and case 2
[442]
is technical score must be more than 50
[444]
which is exactly what we talked about
[446]
and the job is awarded to the bidder
[447]
with the highest composite score with an
[449]
equal weightage
[451]
so nothing has changed from the kind of
[452]
discussion that we have done
[454]
except that
[456]
this condition gets added
[458]
in both cases the call may be cancelled
[462]
if the award price deviates more than 20
[465]
percent from the estimated cost now
[468]
somebody will say why this kind of a
[470]
clause is required
[472]
one of the simplest of reasons that i
[474]
can give you for this is
[476]
that you will recall
[479]
that there is an approval which has been
[481]
taken based on
[483]
some estimates
[485]
for spending a certain amount of money
[486]
on a certain project
[489]
if the
[491]
award price
[492]
deviates
[495]
too much from that especially on the
[496]
higher side
[498]
then
[500]
fresh approvals must be sought before
[503]
the bid is
[504]
awarded and the work is actually taken
[506]
up
[507]
there have to be reasons
[509]
for that there has to be a justification
[510]
which has to be provided to the kind of
[512]
authorities which approved the project
[515]
in the first place
[516]
and so on
[518]
as far as the deviation on the lower
[519]
side is concerned we will talk about it
[522]
at the end of this class today now if
[524]
this rule was to be operated
[526]
then
[527]
in case one
[528]
the technical marks are not being
[529]
considered
[531]
bidder c gets the job being the lowest
[533]
bid because this part does not really
[535]
matter
[536]
this guy here is 101
[539]
it is the lowest and we should check
[542]
that
[543]
the award price which is 101 000
[547]
is within the allowable deviation of 20
[549]
percent from the estimated cost of 100
[551]
000
[552]
now coming to case 2
[554]
the situation becomes more complicated
[557]
because
[558]
bidder c gets disqualified
[562]
not having secured 50 percent marks in
[564]
the technical bid
[566]
and
[567]
its clear that
[568]
this guy has quoted 135 this is 125 and
[571]
this is 130 so no matter who gets the
[574]
job the award value will be
[576]
more than the allowed deviation of 20
[579]
percent from the estimated cost
[582]
and therefore
[584]
the result is cancel the call
[587]
and go for a fresh process now
[590]
if the situation
[592]
on the financial bids was to change
[596]
marginally
[598]
and these were the numbers that we were
[599]
dealing with instead of the numbers in
[600]
the previous table
[602]
so this here just lists the
[605]
conditions that we are applying
[608]
and now we come to evaluation of these
[610]
bids
[611]
bidder c gets disqualified having a
[614]
lower technical score
[616]
now
[617]
here is a situation where
[619]
d
[621]
is a potential bidder
[622]
with 115 points which is within the 120
[626]
allowed by the 20 percent deviation but
[629]
the question is
[631]
will d get the job
[633]
given the fact that
[635]
there is a 50 50 weightage being applied
[638]
to
[639]
the technical bid and the financial bid
[641]
now if we carry out the calculations and
[644]
determine the composite scores this is
[646]
what we get
[647]
bidder b has the highest score but the
[650]
bid value
[652]
is
[652]
125 the technical score is 83
[656]
and his value is 125 and this is in
[660]
excess
[661]
of
[662]
the maximum deviation allowed which
[664]
allows you to go up to 120
[667]
and therefore the call has to be
[668]
cancelled
[670]
so with this discussion here
[672]
i think we have covered several examples
[676]
where we try to give different
[679]
weightages to technical and financial
[681]
bids
[682]
try to evaluate the
[686]
bids based on different criteria
[689]
and also invoke the principle that the
[692]
final
[693]
award value should be
[696]
within a certain
[697]
range of the estimated value
[700]
so having said all that
[702]
let us look at this
[704]
table once again
[706]
which is the financial bid
[708]
for
[709]
4 bidders for a project which was
[711]
estimated to be 100 000 that is the
[713]
numbers that we have been working with
[715]
in an earlier example as well the
[717]
question that we must ask ourselves
[721]
as per the criteria indeed the project
[723]
has to be awarded to c because this guy
[726]
is indeed the lowest bidder
[728]
but please also remember that the bid is
[731]
64 compared to an estimated cost of
[734]
100.
[736]
the question we must ask ourselves
[738]
is it appropriate
[740]
to award the job
[742]
without considering the technical
[744]
aspects of the bidder at all
[746]
or
[748]
whether we should
[749]
award the job to the lowest bidder
[752]
regardless of
[753]
how
[755]
much lower it is compared to the
[758]
estimated cost
[759]
the issue really is
[762]
what is the client looking for
[764]
when we are trying to identify a bidder
[768]
or identify a contractor
[770]
to do a particular project
[773]
the issue is
[775]
we are looking for a technically
[778]
sound bidder who will carry out the
[780]
project at a reasonable cost
[783]
one
[784]
term
[785]
or parameter we have not invoked at all
[789]
is quality
[790]
and that is something which i would
[792]
leave
[793]
to you to think about
[795]
is the client not concerned about the
[798]
quality of the work we are talking of
[800]
technical
[802]
merit or technical performance of
[805]
bidders
[806]
how are we ensuring the quality of the
[808]
job that the
[810]
bidder will do
[812]
is it being completely ignored
[816]
in fact the condition of disqualifying a
[819]
bidder if the technical score is too low
[821]
is an outcome of this principle the
[824]
inherent
[826]
thought process here is that
[828]
for a bidder
[830]
which is technically not
[832]
competent or has a low score
[836]
it is difficult to believe that
[839]
the bidder will be able to do a quality
[841]
job and that is why we fix a threshold
[845]
that at least so much should be the
[847]
score for the bidder to be considered
[850]
for the opening of the
[851]
financial bid
[853]
similarly
[854]
a bid which is too much lower than the
[857]
estimate can also be looked upon with
[860]
suspicion now the question is can we
[863]
have a clause for disqualifying a bidder
[866]
if the bid value is lower than 80
[869]
percent or some such number of the
[872]
estimated cost
[873]
please remember
[875]
that this discussion that we have had
[876]
today is not necessarily something which
[879]
is followed in a ward of jobs but
[882]
the principle or the issue which i
[884]
wanted to highlight through this
[885]
discussion today
[887]
was to draw your attention to the
[889]
importance of carrying out
[892]
a proper technical evaluation of the
[894]
bids independent of the financial
[896]
evaluation
[897]
and
[898]
trying to see
[900]
whether
[901]
or how
[902]
the
[903]
technical marks or the marks obtained
[905]
for the technical performance or
[907]
technical competence how they can be
[910]
incorporated in our system of evaluation
[912]
of bids
[914]
having said all that we must also
[916]
remember that no matter what we do
[919]
if we want to evaluate the bidders for
[921]
technical performance
[923]
the exact procedure as to how the marks
[926]
will be awarded should be declared up
[928]
front
[929]
it should be part of the conditions of
[931]
the contract so that the bidders really
[934]
know that these are the parameters on
[936]
which the technical evaluation will be
[938]
done
[939]
and no
[941]
change should be made after the game has
[944]
started so it is clear from some of the
[946]
examples that we did that depending on
[949]
the weightages that we assigned
[951]
the whole call could be cancelled bidder
[954]
one could get the job bidder two could
[956]
get the job
[957]
and we cannot just have a situation
[960]
where this is left to the whims and
[963]
fancies of the client
[966]
the whole thing is just too serious to
[969]
risk that therefore
[972]
in this day and age when we are talking
[973]
of transparency accountability
[976]
and so on it is very very important that
[979]
these conditions are
[981]
announced up front
[983]
and
[984]
followed in letter and spirit as far as
[986]
the evaluation of bids is concerned
[989]
so with this we come to an end of our
[991]
discussion today
[993]
we will see you in the next class thank
[995]
you
[997]
[Music]
[1015]
[Music]
[1022]
[Music]
[1029]
you