Greetings! In this lesson I'm going to
demonstrate how to do the forward and
[8]
backward path to determine the estimated duration of the project. So here we have
[14]
exercise 9 the air control company
project and the first thing you should
[19]
do when you look at a diagram like this
is review what's on the legend and the
[25]
legend contains early start, early finish,
late start, late finish, duration, slack
[33]
and the ID right now all we have is the
ID and the duration will be doing the
[40]
forward and backward pass to get the
early start and the late finish
[45]
information so to begin this exercise we
start with an early start of 0 now I
[53]
don't want to argue about this some
people want to get into existential
[56]
questions about how can it really start
be a zero but just to do the methodology
[61]
the uses technique we always start with
zero just accept that and make life a
[66]
lot easier so now we simply add and move
do what all the text calls the forward
[73]
pass and so the earliest that activity a
if it takes two days it will be done on
[79]
the second day that's your earliest it
can be done then B can start once a is
[84]
done so can see so c, so can D and so can E. the earliest start is the early finish
[92]
for the preceding activity now we simply
add Early start to the duration, two
[100]
and ten is 12 - for the preceding activity. 2 and 13 15 2 and 18 is 20
ok now we move to the next activity that
[112]
we can look at and that's F and F is a
merge activity which means there's more
[117]
than one activity that has to be
completed before F can start and this is
[123]
where you need to keep in mind
choosing the larger number so the we
[129]
have two early finishes 12 and 15
that didn't come out too well so I'll
[135]
correct that and we choose the larger
number which is 15 because F can't start
[142]
until both C and D are completed C's
done in the 12th but DS not to the 15th
[150]
so f has to wait until DS done the
earliest it can start then is 15 15 and
[156]
15 is 30 and now we have another merge G
can't start until both B and F er done
[163]
early as B is done as the 17 the
earliest F is done is 30 again we choose
[172]
the larger number 30 30 and 10 is 40 and
then finally we have the last activity
[181]
is also a merge activity H can't start
until both G and E are done the earliest
[186]
G is done is 40 the earliest G is done
is 20 we choose the larger number 40 40
[195]
+ 5 is 45 and we would now say that the
earliest time this project could be
[201]
completed is in 45 days assuming days is
the time unit that we're using now the
[208]
late finish we go backwards and this
time we subtract and instead of choosing
[214]
the larger number we choose the smallest
number when we're forced to make a
[219]
choice
so the latest H can finish without
[223]
delaying the project obviously is 45:46
would mean it's a day late so the late
[229]
finish and the early finish for the last
activity are always the same we subtract
[234]
5 from 45 and the late start for H is 40
again the late start and the late finish
[242]
is the latest this activity can start
without delaying the project the latest
[247]
this activity can finish without
delaying the project so now we move back
[253]
we simply transfer the late start to the
late finish of the preceding activity 40
[260]
10 minus 40 is 30 30 into here
is 15 15 minus 30 is 15 we go down here
[272]
we can take care of e 40 18 minus 40 is
remember about your math 22 okay now we
[282]
can begin to see there's a difference
here this is a non critical activity we
[287]
look up at B latest finish for B without
delaying G is 30 15 minus 30 is 15 and
[300]
these two activities off the merge
activity it's both 15 and 15 you've got
[307]
to follow the arrows backwards 13 minus
15 is 2 10 minus 15 is 5 and then we've
[316]
got a bunch of arrows out of activity a
we got a late start of 20 to a late
[324]
start of two late start of 5 and the
late start at 15 we choose the smaller
[332]
number to 2 minus 2 is obviously 0 and
when you have that you know you're in
[339]
good shape and now we subtract to
determine the slack how much an activity
[346]
can be delayed without delaying the
project we subtract the early start from
[350]
the late start and the early finish from
the late finish on these problems
[355]
they'll be identical because there's no
lags we'll talk about legs and I think
[360]
the third problem but for now we do both
and they should be identical so we go up
[367]
here subtract 2 from 22 it's 20 so what
this means is that activity e
[373]
can be delayed the start of activity can
be delayed up to 20 days without
[378]
delaying the project and that makes
sense if you look that activity II has
[383]
an early start of 2 and a late start of
22 the difference between that is 20 so
[389]
it has quite a bit of slack and lo and
behold when we strike subtract the two
[394]
early finish and late finish we get the
event achill 20
[398]
here we have zeros which means delay and
activity D will delay the project this
[406]
is an indication that activity D is on
the critical path and we have three and
[412]
two from 15 is 13 and then we go here
subtract those two
[421]
we got zeros zeros up here and then the
last activity actually has euros and
[428]
then we trace the critical path follow
the zeros in the slack in this case we
[435]
have one critical path I like to
highlight it make it stick out and so ad
[443]
F G H is the critical path a delay in
the duration the estimated duration of
[449]
any one of these five activities will
delay the project if activity D takes 15
[455]
days instead of 13 days it will add two
days to the duration of the project
[460]
if however activity B instead of taking
15 days end up taking 20 days it would
[468]
not delay the duration of the project or
the completion of the project I should
[472]
say because it has a slack of 13 now the
one other thing that we talked about is
[478]
assessing the sensitivity of the network
and that's the likelihood that the
[483]
original critical path will change once
you start the project and that's a
[488]
function of two things one the number of
critical paths and 2 how much slack the
[496]
non-critical activities have here we
only have one critical path which
[501]
suggests it's not very sensitive but we
do have one activity C that only has
[507]
three days of slack the other activities
have quite a bit of slack B and E so you
[515]
would say that this is moderately
sensitive and our only concern is that
[520]
if C is delayed it could become critical
so remember add and choose the larger
[528]
number going forward when you go back
subtract and choose a smaller number