Greetings! In this lesson I'm going to demonstrate how to do the forward and
[8]
backward path to determine the estimated duration of the project. So here we have
[14]
exercise 9 the air control company project and the first thing you should
[19]
do when you look at a diagram like this is review what's on the legend and the
[25]
legend contains early start, early finish, late start, late finish, duration, slack
[33]
and the ID right now all we have is the ID and the duration will be doing the
[40]
forward and backward pass to get the early start and the late finish
[45]
information so to begin this exercise we start with an early start of 0 now I
[53]
don't want to argue about this some people want to get into existential
[56]
questions about how can it really start be a zero but just to do the methodology
[61]
the uses technique we always start with zero just accept that and make life a
[66]
lot easier so now we simply add and move do what all the text calls the forward
[73]
pass and so the earliest that activity a if it takes two days it will be done on
[79]
the second day that's your earliest it can be done then B can start once a is
[84]
done so can see so c, so can D and so can E. the earliest start is the early finish
[92]
for the preceding activity now we simply add Early start to the duration, two
[100]
and ten is 12 - for the preceding activity. 2 and 13 15 2 and 18 is 20 ok now we move to the next activity that
[112]
we can look at and that's F and F is a merge activity which means there's more
[117]
than one activity that has to be completed before F can start and this is
[123]
where you need to keep in mind choosing the larger number so the we
[129]
have two early finishes 12 and 15 that didn't come out too well so I'll
[135]
correct that and we choose the larger number which is 15 because F can't start
[142]
until both C and D are completed C's done in the 12th but DS not to the 15th
[150]
so f has to wait until DS done the earliest it can start then is 15 15 and
[156]
15 is 30 and now we have another merge G can't start until both B and F er done
[163]
early as B is done as the 17 the earliest F is done is 30 again we choose
[172]
the larger number 30 30 and 10 is 40 and then finally we have the last activity
[181]
is also a merge activity H can't start until both G and E are done the earliest
[186]
G is done is 40 the earliest G is done is 20 we choose the larger number 40 40
[195]
+ 5 is 45 and we would now say that the earliest time this project could be
[201]
completed is in 45 days assuming days is the time unit that we're using now the
[208]
late finish we go backwards and this time we subtract and instead of choosing
[214]
the larger number we choose the smallest number when we're forced to make a
[219]
choice so the latest H can finish without
[223]
delaying the project obviously is 45:46 would mean it's a day late so the late
[229]
finish and the early finish for the last activity are always the same we subtract
[234]
5 from 45 and the late start for H is 40 again the late start and the late finish
[242]
is the latest this activity can start without delaying the project the latest
[247]
this activity can finish without delaying the project so now we move back
[253]
we simply transfer the late start to the late finish of the preceding activity 40
[260]
10 minus 40 is 30 30 into here is 15 15 minus 30 is 15 we go down here
[272]
we can take care of e 40 18 minus 40 is remember about your math 22 okay now we
[282]
can begin to see there's a difference here this is a non critical activity we
[287]
look up at B latest finish for B without delaying G is 30 15 minus 30 is 15 and
[300]
these two activities off the merge activity it's both 15 and 15 you've got
[307]
to follow the arrows backwards 13 minus 15 is 2 10 minus 15 is 5 and then we've
[316]
got a bunch of arrows out of activity a we got a late start of 20 to a late
[324]
start of two late start of 5 and the late start at 15 we choose the smaller
[332]
number to 2 minus 2 is obviously 0 and when you have that you know you're in
[339]
good shape and now we subtract to determine the slack how much an activity
[346]
can be delayed without delaying the project we subtract the early start from
[350]
the late start and the early finish from the late finish on these problems
[355]
they'll be identical because there's no lags we'll talk about legs and I think
[360]
the third problem but for now we do both and they should be identical so we go up
[367]
here subtract 2 from 22 it's 20 so what this means is that activity e
[373]
can be delayed the start of activity can be delayed up to 20 days without
[378]
delaying the project and that makes sense if you look that activity II has
[383]
an early start of 2 and a late start of 22 the difference between that is 20 so
[389]
it has quite a bit of slack and lo and behold when we strike subtract the two
[394]
early finish and late finish we get the event achill 20
[398]
here we have zeros which means delay and activity D will delay the project this
[406]
is an indication that activity D is on the critical path and we have three and
[412]
two from 15 is 13 and then we go here subtract those two
[421]
we got zeros zeros up here and then the last activity actually has euros and
[428]
then we trace the critical path follow the zeros in the slack in this case we
[435]
have one critical path I like to highlight it make it stick out and so ad
[443]
F G H is the critical path a delay in the duration the estimated duration of
[449]
any one of these five activities will delay the project if activity D takes 15
[455]
days instead of 13 days it will add two days to the duration of the project
[460]
if however activity B instead of taking 15 days end up taking 20 days it would
[468]
not delay the duration of the project or the completion of the project I should
[472]
say because it has a slack of 13 now the one other thing that we talked about is
[478]
assessing the sensitivity of the network and that's the likelihood that the
[483]
original critical path will change once you start the project and that's a
[488]
function of two things one the number of critical paths and 2 how much slack the
[496]
non-critical activities have here we only have one critical path which
[501]
suggests it's not very sensitive but we do have one activity C that only has
[507]
three days of slack the other activities have quite a bit of slack B and E so you
[515]
would say that this is moderately sensitive and our only concern is that
[520]
if C is delayed it could become critical so remember add and choose the larger
[528]
number going forward when you go back subtract and choose a smaller number