What Are the Three Most Important Illinois Mechanics Lien Waiver Forms? - YouTube

Channel: unknown

[0]
[Music]
[10]
everybody in design and construction
[11]
knows that it's important to collect
[13]
waivers of lean when periodic payments
[16]
are made
[16]
but lean waivers are very misunderstood
[18]
particularly where i live in illinois
[21]
because the lean act is not just about
[24]
lean claims what people need to
[25]
understand is that the illinois
[27]
mechanics lien act
[28]
is prescriptive it sets out a
[31]
process that a variety of different
[35]
parties who are involved in designing
[36]
construction need to abide by
[38]
it's particularly important for project
[40]
owners to understand
[42]
the requirements of the illinois
[43]
mechanics lien act if they want to avoid
[46]
some of the perils that come along with
[48]
mechanics lanes like having to pay for
[50]
the same work twice
[51]
i discussed this in other videos so i
[52]
won't go too deeply here
[54]
but i will say that illinois project
[56]
owners at least
[58]
on private projects need to understand
[62]
that the mechanics lien act will provide
[65]
certain red lights and certain green
[66]
lights for when they can
[68]
and cannot make payments and when you
[70]
are collecting
[71]
payment documents from a contractor or a
[75]
design professional
[76]
on a monthly basis you need to
[77]
understand what it is that you're
[79]
looking for
[80]
and it's not just good enough to collect
[83]
the piece of paper that says lean waiver
[85]
on the top
[86]
you need to be concerned about the
[88]
content of that document
[90]
you need to be concerned with what is
[92]
the form of lien waiver
[94]
that you're receiving and there are
[95]
three specific forms of lean waiver that
[97]
i'm going to cover today but before i
[99]
get into that i want to make the point
[101]
that if you are only focused on
[103]
collecting lien waivers
[105]
then you have skipped an important step
[108]
because the illinois mechanics lien act
[110]
requires
[111]
project owners to collect sworn
[114]
statements from the parties that they
[116]
hire for design
[117]
and construction services and these
[119]
sworn statements are going to be
[122]
a snapshot of what their contract looks
[124]
like at that moment
[125]
what was the original amount of the
[127]
contract what were the change orders
[129]
what is the adjusted contract amount if
[132]
there are
[133]
subcontractors under a general
[135]
contractor the same information what was
[137]
their contract originally
[138]
how has it been changed how much have
[140]
the parties been paid
[142]
how much are they remaining to be paid
[144]
because it is the content of those sworn
[146]
statement documents
[148]
that informs a well-advised owner what
[152]
the content
[153]
of the lien waivers ought to be
[156]
and that's true regardless of the form
[159]
of lean waiver and there's three in
[161]
illinois
[161]
that are commonly used although they're
[163]
not much understood and the first one
[166]
that i want to talk about is perhaps the
[168]
least understood and that
[170]
is the waiver of lien to amount
[174]
okay there are three kinds wave
[176]
revolution to amount
[177]
waiver of lien to date and final lien
[179]
waiver the waiver of lien to
[181]
amount has language in it which says
[184]
that
[184]
the party that's being paid is giving up
[187]
their right to make a lien claim on a
[189]
private project
[190]
for the amount of money that is listed
[193]
in
[193]
the lien waiver and so where is this
[196]
commonly used oftentimes at the
[198]
beginning of the project
[200]
if a party requires a down payment uh
[203]
you know twenty thousand dollars at the
[204]
time of contract signing
[206]
but there's been no work done to date
[208]
it's appropriate to collect
[210]
a waiver of lien to amount but when you
[213]
move into the project and you begin to
[215]
have monthly payment applications
[218]
uh what you commonly see is a switch to
[222]
the
[222]
waiver of lien to date form now that's
[225]
not always true
[227]
there are instances where it would make
[228]
sense to collect a waiver of land to
[230]
amount
[231]
at various points throughout the project
[233]
other than just at the outset but it is
[235]
common
[236]
for contractors payment applications for
[238]
example to request a certain amount of
[241]
payment
[242]
for the work that they have done up to a
[243]
certain date and it's common
[245]
for the contractor to offer up to the
[247]
owner not just that sworn statement
[249]
that is so very important but also
[252]
waiver of lien
[253]
in the form of waivers of lien to date
[256]
because they are giving up
[257]
their right to claim a lien for the work
[260]
that they did
[261]
up to the date of the application for
[264]
payment
[266]
now the third kind is probably the
[268]
easiest to understand
[269]
that is the final waiver of lien and of
[272]
course the final waiver of lien
[273]
is what an owner is going to collect
[276]
from someone that they've hired
[277]
to do design construction services or
[280]
their lower tier parties subcontractors
[283]
uh you know other types of design
[284]
consultants at the end of the project
[286]
when the work is done and so what you
[290]
will see
[290]
obviously at the top of these different
[293]
forms of lien waiver is their title
[294]
you'll see
[295]
waiver of lien to amount you'll see
[298]
waiver of lean to date and you'll see
[299]
final lean waiver but if you dig
[301]
into the text of those forms
[305]
of lien waiver at least in illinois at
[307]
least on private projects what you're
[309]
going to find
[310]
in the fine print is that a waiver of
[312]
lien to amount is going to say i'm
[314]
giving up my right to lien for the
[315]
amount stated
[316]
a waiver of lien to date is going to say
[318]
i'm giving up my right to lien for work
[320]
that i did before the date indicated
[322]
and the final wave of lien is going to
[323]
say that i am giving up my right to lean
[326]
for any work that i did before today's
[328]
date or after today's date because we're
[330]
done
[331]
and uh you know while there is no
[334]
statutory form in illinois and that's
[336]
not
[336]
true with other states there are other
[338]
states where it's included right in
[340]
their lean act this is the form of lien
[342]
waiver
[342]
in illinois even though there is no
[344]
specific statutory form
[346]
there are some very commonly used forms
[349]
of lean waiver
[350]
that would be familiar to most every
[353]
contractor that you would encounter
[355]
certainly those that are reputable
[356]
certainly those that are experienced
[358]
and it's that form of lien waiver and
[361]
it's that form of sworn statement
[363]
the commonly used ubiquitous ones that
[365]
you're going to want to stick with
[367]
sometimes i will see on projects a
[370]
contractor creating their own
[371]
form and you know the problem with that
[374]
is
[374]
is that it may not marry up with the
[377]
requirements of the illinois lean act
[379]
because if you collect a sworn statement
[381]
that doesn't have the right content
[383]
or you collect a waiver of land that
[384]
doesn't have the right content
[386]
it might not serve its purpose under the
[388]
illinois lean act and so while there is
[390]
no
[391]
official version that is handed down
[394]
by the illinois general assembly there
[396]
are some very
[397]
commonly used forms that any
[399]
construction attorney or any reputable
[401]
contractor or any owner
[403]
that is experienced in designing
[405]
construction would immediately recognize
[407]
in forms that that are other types forms
[410]
which are of a contractor's own creation
[413]
for example are typically not going to
[415]
be adequate for me
[416]
when i represent real estate developers
[419]
and project owners
[420]
on illinois private construction
[423]
[Music]
[429]
projects