馃攳
Finally! I started building my own house. Pt1- foundations and concrete slab - YouTube
Channel: lignum
[16]
So it begins.. :)
[20]
Hammering the posts of wall and foundations axes.
[30]
Marking each post at the same elevation at which the finished ground floor will be.
[41]
Screwing on the planks at those markings and making sure they are level.
[59]
Lowering a string to each small surveyor post. These posts mark the corners of foundations and were placed there by licensed surveyor couple of days earlier..
[74]
String is then pulled to touch the vertical strings and where it touches the plank, we mark it..
[82]
small screws are screwed on to the markings so strings can pe puled between them.
[91]
We marked the area where the top soil has to be removed. Cca 1m offset from the foundations plus the driveway..
[101]
Removing the 20-30cm of top soil.
[113]
Arrival of the most important table and bench:)
[120]
Placing a geo-textile membrane. It keeps the different layers from mixing and increases the ground load bearing.
[140]
A lot of gravel..
[145]
Strings are again pulled to mark the foundations.
[152]
Posts are hammered where the strings intersect. Those are the corners of the foundations.
[160]
A few post are added in between so it's easier to mark..
[180]
Compacting the gravel..
[185]
And we start with the foundation dig..
[222]
Foundations will sit on 30cm of compacted gravel.
[245]
The crane came from the other house construction site you can see on this channel.
[257]
It has 18 meters reach, 1ton load capacity at 10m, 600kg at 18m.
[268]
Rebar is here..
[276]
5 14mm rods at the bottom, 5 14mm at the top, 2 10mm in the middle, 8mm stirrups every 25cm.
[293]
Testing the level of compaction with the deflectometer.
[337]
Placing the vertical rebar anchors for RC posts.
[354]
Anchors for RC walls.
[359]
We used 5cm extruded polystyrene for shuttering and insulation of foundations.
[371]
Wooden stakes keep the shuttering at the right distance and will be removed during the concrete pour.
[394]
Reinforcing the top part of Polystyrene so the pressure of the concrete doesn't brake it.
[413]
Tool shack foundations wont be insulated so no polystyrene here..
[426]
Concrete is here! First pour of many..
[442]
Concrete is C25/30 grade.
[452]
Vibrating and pulling out the wooden stakes.
[473]
Removing the wooden reinforcements..
[486]
We marked and cut the excess polystyrene to a level plane.
[495]
This will be the level of the bottom of the slab.
[503]
We filled the space between the foundations with gravel and compacted it to level 8cm lower.
[526]
Placing the slab shuttering.
[532]
Testing the level of compaction again..
[541]
Those 8cm height difference is filled with polystyrene. It will insulate the bottom of the slab.
[552]
Q257 rebar meshes.
[563]
Here in the left corner you can see water and electricity pipes, unfortunately I didn't have the chance to film how they were placed..
[570]
Some concrete blocks to keep the bottom and the top meshes at the distance.
[581]
Slab pour day..
[587]
This slab is 14 cm thick.
[618]
That's all for this episode, See you next time:)
Most Recent Videos:
You can go back to the homepage right here: Homepage





