馃攳
MS Project Planned Percentage Complete Vs Actual Percentage complete - Updated Improved version - YouTube
Channel: Niks Projects
[0]
so when I created the original video
five years ago I got a lot of feedback
[4]
that the screen recording was not clear
enough for people to understand
[9]
so anyway today's video is a recreation
of that older video hopefully this time
[14]
the screen recording is clear because
I'm using a different software and also I was
[21]
getting a lot of comments can can you
show this in MS Project 2016
[27]
some people have comments that the
formula was giving error I received a
[33]
lot of feedback that the formula did not
work at the summary task level so I'm gonna
[39]
show it today so nothing changed from a
formula or step perspective I'm gonna
[45]
show it today so you guys can follow
along with me and understand what
[50]
exactly you need to know so I'm just
gonna create a new simple project let's
[65]
open a blank project we will set the
project start date today's first so let
[73]
me go back to him Monday 22nd will
create a two week project starting
[80]
October 22nd and the current date is
said so that's set under the project
[89]
information section we call it a two
week project week one we have day one
[102]
day two day three day four day five so
I'm just gonna copy for the second week
[112]
and paste it and we call the second week
as week two all this is part of the
[119]
two-week project so on the task I'm
gonna intend it and then the first five
[125]
days goes under week 1 and the second
five days goes under b2
[132]
all this has one day duration so I'm
just gonna select all that go to
[141]
information and say duration is one day
I'm also gonna link all this tasks so
[151]
click on the link so it's sequential II
followed one after another so that is
[158]
just to keep things simple and now we
have the basic project structure so
[167]
before we go into next projects and copy
the formula one thing to ensure is that
[176]
you have baselined the project so I'm
gonna go to project and set baseline
[188]
this is very critical because all the
calculations are done based on the
[194]
baseline dates so just make sure you
baseline the project because I'm just
[199]
gonna exactly mimic what you guys are
gonna do copy pasting the formula right
[207]
I just want to show that the formula
works whether it's MS Project 2010 2013
[213]
or 2016 it's all the same I have not
changed anything and I just wanna show
[221]
you a series so that you guys can follow
along I think the previous video was not
[229]
clear enough from a screen capture
perspective so I'm not going to explain
[235]
the details put in here I'm just gonna
make it faster copy paste the formula
[242]
and as I do I'm gonna explain you all
these things so how to do it and the
[250]
formula so in order to do it you need to
basically create a new column number as
[257]
the format and call it as duration in
days and then I'm just gonna copy paste
[262]
this
copy go to the project and then we said
[271]
we want a new column called number I'm
gonna right-click click on custom fields
[282]
rename they said we wanna call it as
duration in days and click on formula
[290]
radio button and then just copy paste
the formula and click OK click OK and
[300]
then ok so we just completed the step
one right so you know whatever you are
[307]
seeing interation in days should match
to what you have here because if you
[313]
change this to two days it should
automatically change to two and the
[319]
summary also should show six instead of
zero so I'm gonna change it back to one
[325]
the reason it did not change is because
we did not apply the formula for the
[331]
summary task so you can't go back to
custom fields and then we did the
[337]
formula but then you have to ensure that
you are using the formula for the
[343]
summary rows so click on use formula and
then click OK now you can see the
[351]
summary tasks also has the formula
applied so it matches to the duration on
[359]
the MS Project so duration minimis
project is stored as in minutes even
[366]
though displays here as days it is
actually stored in minutes and that's
[372]
the reason why we have to copy paste the
formula and convert into days so this is
[380]
the formula to convert the duration
which is told natively in minutes into
[386]
days so that's all what this step is now
if you go back to the website the step
[394]
two is to calculate the elapsed
so again we are to insert a new number
[401]
to column call it elapsed days and
copy/paste this formula so this is where
[408]
most of you were getting error as I get
a lot of feedback that this formula is
[414]
not working so just watch carefully here
and you can see what error I'm getting
[423]
and how you can resolve it so I'm gonna
copy the formula and we'll select a new
[430]
column for number two and rename it as
elapsed days so go to the MS project
[437]
right click number insert a new number
column I'm gonna go to custom fields
[448]
rename it as elapsed days click OK and
then come to formula click the formula
[461]
button just paste it and click OK
so here I also got the error that the
[471]
formula has some issue so click OK and
what it does is it's not the error in
[479]
the syntax but for some reason you just
have to retype in a way where the error
[486]
is highlighted so click on dad just
retype the same thing click OK and it
[494]
works and click OK now here is where you
see error right so the reason you're
[503]
seeing error is now it is calculating
the elapsed days and it doesn't have a
[511]
reference it doesn't know what is my
reference point so what I mean by that
[517]
is if you go to project information you
have to set the status date so by
[524]
default it's not applicable so just
choose today's date so today is November
[529]
1st for me
being on that click okay now you see the
[535]
elapsed days column is showing up again
it's not working at the summary tasks
[541]
level so again right-click go to custom
fields and under the summary summary
[550]
rows option use formula and that should
take care of it so what it is doing is
[558]
it is comparing your baseline date and
calculating how many days is already
[568]
over right so today's November first so
it's it's stating that we have completed
[576]
nine days of the project because it's
November 1st and it's gonna end on 2nd
[582]
so as per the plan dates we already
consumed nine days so that's what this
[588]
column is now we are done with if we are
done with the second step right so at
[599]
any point you can go back and say ok let
me calculate the elapsed days as off
[605]
let's say October 23rd it should be only
two days right so you click on the
[612]
status date and you say it's today's
October 23rd you see the elapsed days is
[621]
going back to two days so that's how it
is calculating the elapsed tapes based
[626]
on the status date so just make sure
that you are setting the status they
[632]
tried to have the calculations correctly
now going back to website for the final
[641]
step which is step number three not the
final step so here we are actually
[646]
calculating the planned percentage
complete so again the formula is simple
[652]
number two divided by number one insert
a new column called number three just
[659]
rename it go to custom fields rename
planned percentage okay
[668]
click the formula radio button click
formula and say you can copy paste by
[675]
the way I'm just gonna type number two
divided by number one okay and then
[683]
apply to summary row okay and now you
have the planned percentage complete so
[690]
it saying it's ninety percent complete
the actual percentage may not be ninety
[698]
but this is what we are calculating
right if we would have followed the plan
[702]
baseline dates what person date should
the project be in at certain date now
[710]
the next and last final step is just to
format this into a percentage type of
[720]
field so it has to be a text so I'm
gonna click that again coming back to
[726]
the web side it said text we are calling
it as planned percentage complete and
[734]
then copy paste the formula copy and
then go here and then paste it right
[742]
click custom fields formula and then
paste it okay okay again it's showing me
[757]
an error so you just have to delete that
portion and retype the same thing
[763]
there's nothing wrong with the formula
for some reason it doesn't take any copy
[770]
paste so just retype it and say use
formula for summary rows and click OK
[776]
and there you have it so once you have
this you can always rename it what did
[783]
we call in here as planned percentage
complete just copy that and right click
[795]
custom fields
renamed paste okay okay
[803]
so this is what we were calculating
manually right and the the column that
[810]
is available in Emma's project is the
percentage complete so you go back to
[815]
let's say this is as soft 23rd right you
go back to the project information click
[822]
on the status date and let's say as of
23rd October 23rd ideally we should have
[832]
completed 40% but we have only finished
34% so we are running behind but there
[839]
could be chances that some let's say
this did not had any dependency on you
[846]
know number 7 and let's say he finished
this 100% right so if you look at the
[855]
overall percentage for the project as of
23rd you were only planned to finish 20%
[865]
so we actually finished 27 percent right
so that's where you can see the actual
[871]
value even though from a date
perspective it may not be aligning to
[876]
what your complete versus what your
planned but at the overall project
[881]
perspective you are actually ahead of
schedule because you have completed some
[887]
tasks that are not scheduled to start
until certain date right so so just
[895]
wanted to show this example once you
have this column defined you can right
[900]
click and hide all this so you have this
planned percentage versus actual
[906]
percentage complete so at any point of
time you can compare what was what was
[912]
supposed to be the percentage complete
if you would have followed the planned
[917]
dates against the actual percentage
complete so I hope this helped you guys
[922]
and if you like this video give me a
thumbs up and consider subscribing to
[927]
this channel for more videos like this
all right take care guys
Most Recent Videos:
You can go back to the homepage right here: Homepage





