Earned Value Management | EVM | PMP Questions and Answers 1 | PMP Exam Prep - YouTube

Channel: Sunny Sensei

[0]
In this lesson, we will solve some problems on
[3]
Earned Value Management
[6]
Here is the first problem...
[9]
You are working on a project that will last for 5 months.
[13]
As per the plan, Activity A
[15]
starts in the first month and finishes
[18]
at the end of the third month.
[21]
Activity B will be performed in the second
[24]
and third months.
[27]
Activity C starts in the mid of the third month
[30]
and lasts for a month.
[33]
Activity D begins at the start of the fourth month
[37]
and has a duration of two months.
[40]
The estimated cost of each activity is
[44]
Activity A $20,000
[47]
Activity B $50,000
[49]
Activity C $10,000
[52]
Activity D $30,000
[57]
What is the Planned Value
[58]
at the end of the third month?
[61]
A: $70,000
[64]
B: $80,000
[67]
C: $75,000
[70]
D: $30,000
[74]
Please pause the video and try this problem.
[81]
Alright ....
[83]
we have a project that is 5 months long
[87]
and we are supposed to find the planned value
[90]
at the end of the third month
[95]
What is the Planned Value?
[97]
It is the planned cost of the activities
[99]
that we are supposed to complete
[101]
from the start of the project
[103]
till the end of the third month.
[106]
Activity A starts in the first month
[109]
and finishes at the end of the third month.
[113]
$20,000 is the planned cost.
[117]
This activity ends before the end of the third month
[120]
so, 100% of this amount contributes
[123]
to the Planned Value.
[125]
Activity B is performed in second and
[128]
third months
[131]
and the planned cost for activity B is
[134]
$50,000
[137]
Again, we plan to finish before the end
[140]
of the third month.
[141]
All of this money will contribute to the Planned Value.
[146]
Activity C starts in the middle of the third month
[150]
and ... When does it finish?
[153]
It is one month long and will therefore finish
[156]
in the middle of the fourth month.
[160]
Only 50% of this activity
[163]
will be completed in the 3rd month.
[167]
Total cost of this activity is $10,000
[171]
Half of $10,000 ... or
[174]
$5000 will be consumed
[177]
before the end of the third month.
[180]
Activity D Starts at the beginning of fourth month
[183]
and has a duration of two months.
[187]
This is after the third month and will not contribute
[190]
to the Planned Value.
[192]
We can simply ignore Activity D.
[195]
Planned Value at the end of the third month is
[198]
$20,000 from activity A
[201]
plus $50,000 from Activity B
[205]
plus $5,000 from Activity C
[209]
The Planned Value is
[212]
$75,000
[214]
C is the correct choice.
[218]
Let’s move to the next problem.
[222]
You are 5 months into a 2 year long project.
[226]
The following numbers are reported by the project manager.
[231]
EV equals $120,000
[235]
CPI is 1.1
[238]
SPI is 1.0
[242]
Which of these statements is correct?
[245]
A. The project is under budget
[247]
and is also ahead of schedule
[250]
B. The Cost Variance of the project
[253]
is negative and the project is on schedule
[257]
C. The Schedule Variance of the project
[260]
is zero and the Cost Variance of the project
[263]
is positive
[265]
D. The project is on schedule
[268]
but is over budget
[271]
Please pause the video and try the problem.
[278]
Every option talks about budget and schedule.
[281]
Let’s check the schedule first.
[283]
The first choice says …
[285]
the project is ahead of schedule
[289]
Option B says project is
[291]
on schedule.
[294]
Option C says
[296]
schedule variance of the project is zero.
[301]
Zero schedule variance means
[303]
the project is on schedule.
[309]
D also says
[310]
the project is on schedule.
[314]
SPI is 1
[317]
This means the project is on schedule.
[323]
A is incorrect.
[326]
We are left with 3 options.
[330]
We will look at the cost now.
[332]
Option B says Cost Variance is negative.
[336]
This means the project is over budget.
[340]
Option C says Cost Variance
[342]
of the project is positive.
[345]
This means project is under budget.
[349]
Positive Cost Variance is good.
[352]
Option D says project is over budget.
[358]
The CPI for the project is 1.1
[362]
It is more than 1.
[364]
The project is under budget.
[367]
Clearly, option B and option D
[370]
are incorrect.
[372]
Option C is our choice.
[375]
Let’s look at one more problem.
[379]
You are assigned as a consultant
[382]
to an ongoing project.
[383]
Before your first meeting with the project manager,
[386]
you come across the following information
[388]
about the project.
[390]
No other details about the project are known to you.
[394]
BAC = $2,120,000
[400]
CPI = 0.65
[405]
SPI = 0.9
[409]
Planned Project Duration = 18 months
[413]
How can the current situation be described?
[417]
A. It is impossible to complete the project
[420]
at the budgeted cost
[423]
B. The project is 35% over budget
[427]
C. The project is 65% under budget
[432]
D. 10% of the planned work
[435]
has been completed till now
[438]
Again, I would strongly recommend
[441]
that you pause the video and try this problem yourself.
[448]
Alright, let’s start with option A.
[452]
It is impossible to complete the project
[455]
at the budgeted cost.
[457]
Budgeted cost is the BAC.
[461]
$2,120,000 in this example.
[465]
Is it impossible to complete the project
[468]
at this budget?
[470]
We cannot be sure about that.
[472]
The project is 18 months long.
[475]
It is possible that the project is still
[478]
in the initial stages.
[479]
Even though the CPI, at the moment
[482]
looks pretty bad, there is enough time
[485]
to improve the cost performance of the project
[487]
and get it back on track.
[489]
This is just a guess.
[491]
There is simply not enough information for us
[494]
to conclusively claim that the project
[496]
cannot be completed within the budget.
[498]
A is incorrect.
[501]
Let’s move to option B.
[503]
The project is 35% over budget.
[507]
The CPI is 0.65
[512]
This means for every dollar spent,
[514]
only $0.65
[517]
worth of activities are completed.
[520]
Ideally, for every dollar spent, we want
[523]
$1 worth of activities to be completed.
[527]
The gap
[528]
$1 minus $0.65
[533]
is $0.35
[536]
or 35% in relative terms
[541]
We are 35% over budget.
[544]
B is clearly the correct choice.
[548]
Still, let’s check C and D also.
[552]
C is incorrect.
[553]
We have already proved that the project
[555]
is 35% over budget.
[558]
What about the D?
[560]
10% of the planned work
[562]
has been completed till now.
[564]
SPI is 0.9
[567]
or 90%
[570]
We have completed 90% of the planned work.
[574]
10% is incorrect.
[577]
B is our choice.
[580]
Let’s move to the next problem.
[584]
You are reviewing a project
[586]
that was completed last month.
[588]
The planned project budget was $1,000,000
[591]
and the planned execution time was 2 years.
[594]
But, the project was over budget
[597]
by 13% and took an extra
[600]
4 months to complete.
[602]
Which of the following is not true about this project?
[606]
A. The Earned Value of the project is $1,000,000
[611]
B. The SPI of the project is 1
[615]
C. The Schedule Variance of the project is negative
[619]
D. The CPI of the project is less than 1
[624]
Please pause the video
[625]
and try to find the correct choice.
[632]
Alright ...
[634]
we have to find the statement that is not true
[637]
statement that is false
[640]
Option A says…
[642]
Earned Value is $1 million.
[645]
The project budget is also $1 million.
[648]
Budget is BAC or
[651]
Budget At Completion.
[655]
BAC indicates the total value
[658]
that the project should create.
[660]
When a project is completed, the value created
[663]
or Earned Value equals
[665]
BAC
[666]
A is TRUE.
[670]
Let’s move to B.
[672]
SPI of the project is 1.
[676]
We know that the project was delayed by 4 months.
[680]
When a project is complete, SPI
[683]
is always 1
[685]
The overall delay doesn't matter.
[688]
SPI is Earned Value divided by
[690]
Planned Value
[693]
EV or the value of work done
[695]
at the end of a project is BAC
[700]
We talked about this in option A.
[703]
Total Planned Value for the project
[705]
is also BAC
[707]
so, SPI is 1
[711]
Option B is also TRUE.
[716]
Option C says ...
[718]
Schedule Variance is negative.
[721]
SPI is 1. So,
[724]
Schedule Variance will be zero, not negative.
[728]
Option C is FALSE
[731]
Let's look at Option D also.
[735]
CPI of the project is less than 1
[739]
We know that the project was over budget
[741]
by 13%
[743]
CPI should indeed be less than 1
[747]
D is also TRUE
[750]
We are looking for a statement that is NOT TRUE
[753]
A, B, D are TRUE
[757]
so, C is our choice
[761]
Let's look at the next problem ...
[765]
You have approached the management
[768]
for additional funding for your project.
[770]
In your presentation,
[771]
you have captured these critical parameters.
[775]
BAC = $120,000
[779]
PV = $40,000
[783]
AC = $40,000
[787]
CPI = 0.8
[791]
But, one person in the audience
[793]
requested for Cost Variance.
[796]
What should be your response?
[799]
A. CPI and Cost Variance
[802]
are related parameters.
[804]
As we already know CPI, we don’t need Cost Variance.
[809]
B. The information in the presentation
[812]
is not enough for calculating Cost Variance.
[815]
Cost Variance will be presented in the next meeting.
[820]
C. The Cost Variance of the project
[823]
is related to CPI.
[825]
The Cost Variance is minus $8,000
[830]
D. Schedule Variance is also an important parameter.
[834]
Schedule Variance and Cost Variance will be presented
[837]
in the next meeting after detailed analysis
[842]
Please try to solve the problem yourself.
[850]
The management wants to know the Cost Variance.
[853]
Let’s find the best response.
[856]
We will start with option A.
[859]
CPI and Cost Variance are related parameters.
[863]
That’s right.
[865]
Both these parameters
[866]
check the project cost performance.
[869]
We know the CPI.
[871]
But does that mean we don’t need the cost variance?
[875]
CPI tells us how much work is done
[878]
per dollar spent.
[881]
It gives us a relative assessment of the cost deviation.
[885]
On the other hand cost variance gives us
[888]
the cost gap
[889]
in terms of dollars.
[892]
Both these parameters are important
[894]
and provide us with different perspectives.
[897]
Option A is incorrect.
[901]
Option B, Option C and Option D
[904]
all talk about cost variance.
[908]
Option D also talks about Schedule Variance.
[913]
This is a little strange.
[915]
The request is for Cost Variance.
[919]
This option is unlikely to be correct.
[922]
Still let’s check carefully.
[925]
We will focus on Cost Variance.
[928]
Cost variance equals Earned Value minus Actual Cost.
[934]
Actual Cost is dollar 40,000
[937]
What about the Earned Value?
[940]
CPI is 0.8
[944]
CPI is Earned Value by Actual Cost.
[948]
Therefore, Earned Value is
[952]
$32,000
[956]
EV is $32,000
[960]
AC is $40,000
[964]
so, Cost Variance is
[967]
minus $8000
[971]
B and D are incorrect.
[974]
C is the correct choice.
[978]
How many of these 5 problems did you get right?
[981]
Please let me know in the comments.
[984]
All the best with your PMP!