Hello friends, welcome back to my youtube channel. In this video, I am going to explain the construction contract
[7]
part three in this part three, I I will explain the clauses of the
[13]
Contract this is just, we can say there the general condition of contract and the special condition of contract. So this is very
[21]
important part
[23]
for the construction contract so watch this carefully and I request you to watch this till end and
[31]
If you like this video, so please click on the like button. First
[35]
I am going to explain the general condition
[37]
contract condition, that set the minimum performance requirements for the contractor and are common to all types of contracts these
[46]
Conditions are also include the rights and well as contractor involved
[52]
GCC's are
[54]
Integral part of the contract. So this is the definition of the contract. So let us start the
[61]
Important process of the general condition in this definition clause we define what is engineer architect
[68]
contractor client own virtual completion working time and other
[73]
Terms used in the contract. We explain here the second
[77]
What is the scope of work in this is preferred date of commencement?
[82]
date of commencement
[84]
means at what date the work will start by the
[88]
contractor so we can say that that is the
[91]
starting date of the
[93]
project
[94]
nature of contract nature of contract on some contract or cost plus contract
[99]
So this is the nature of contract next one is all-inclusive with rates
[105]
We define whether the rates are inclusive of taxes or exclusive of taxes is exclusive or increase will be defined in this
[112]
clause
[113]
Next one is insurance in this insurance part
[118]
Like the always policies
[121]
So the contractor will provide the all risk policies and any other incidents required
[127]
So who will be responsible whether the contract we'll do it or the client will do so in this incidence path
[134]
We define all these things it's it's very important clause Italy
[139]
Lower regulations in this level of regulation conductor will be responsible for on labor laws such as payment wages
[146]
It is what I explained here definition scope of work date of commencement
[150]
nature of contract
[152]
all-inclusive rates
[154]
incidence and labor regulations
[158]
Few of them are still remaining. So let's go to the next slide
[166]
ESI and EPF es contribution if it like
[170]
Employees state incidence. This is ESI. And
[173]
Employees Provident Fund EPF. So the contractor will also responsible for this thing
[180]
So next one is mode of measurement and any other method will be followed
[185]
so in this mode of measurement the description is
[189]
given
[190]
Next one is payment how the payment will be given
[193]
I mean there is any advance payment and after some meeting they are running. I can't be how the payment will be
[200]
Released there is any a document will be released
[202]
so all these payments realistic things is mentioned in this payment clause next one is extra attempts of
[209]
Substituted item how the extra item is defined. I mean whether the person the profit is 15%
[216]
cost plus materials plus labor whatever is
[220]
In it is defined how extra item a subtitle item will be there. You are derived
[226]
So this is also important clause
[230]
Next one is time for completion
[232]
so as
[234]
You know that the what is the time of completion we mention is whether it is a one-year project or two years
[240]
So by on what date this project will be completed
[245]
next one is virtual completion of work virtual completion wall of work is actually
[251]
completion with ex nag lives we give a
[254]
Late in the construction field the safety clause it is all safety words
[260]
to be followed and if there is any penalty if the contractor not
[264]
following the safety codes, so we mentioned so I
[267]
Explained ESI and EPF mode of measurement payments extra time substitute items time for completion
[274]
Virtual completion of Worth and safety now there is a few
[279]
Clauses also left in the general condition of contracts. So let's go to the next slide in this next slide
[286]
This is the dispute settlement and arbitration
[289]
So a form of alternative dispute resolution is a way to resolve disputes outside the code
[296]
so this is the
[297]
Arbitration is not a system by which you can get with
[302]
settlement outside of the important
[305]
Liquidated damages if project is delayed. So what the penalty will be
[311]
Imposed on the contract and so this is called the liquidated damages
[316]
Generally the liquor more than the and x 1.is extension of time. So in what sir comes even to the contractor?
[325]
Guarantees of the work whatever the executed whatever the work be excreted by the contactor
[331]
so the conductor will give the guarantee for that defect liability period
[335]
in this different level tepees withheld with the
[340]
Client and after the quick liability period that security or attention money is released. This is a force majeure force
[349]
Every condition in which in what?
[352]
circumstances the delays not considered if any delays is happened, but there is some
[359]
circumstances if they're between two countries or
[363]
Any earthquake happens will these conditions then glaze not
[370]
Plasma nation termination is the conditions to terminate the contract
[376]
by the client or by the control
[378]
I explained here dispute settlement an arbitration liquidated damages extension of time guarantees defect liability period
[388]
For scenario
[391]
Termination
[394]
So these all were the general condition of contract now, let's move to a special condition of contract a
[402]
Special condition of contract what is a special condition of on to the condition? Which do not fall under?
[406]
General conditions and is specific for the particular good. So this is called a special condition
[412]
so special condition of contract
[415]
first is performance bond a bond issued by a migrant in the
[421]
fulfillment of a particular
[424]
Contract this is a performance
[426]
Next one is earnest money and unless money is a specific form of seeking to deposit made in some major
[434]
Transactions such as real estate dealings are required by some official procurement
[439]
Process the serious and willing to demonstrate an earnest of good faith
[445]
wanting to complete the transaction, so whether he is
[450]
Serious or not for that there. They have to deposit some money. Next one is mobilization of us
[456]
It was given to the contract of the value of the project
[460]
Next one is water electricity
[462]
With that client will provide free of cost for contractor will arrange. So this is a water electricity
[469]
next one is
[471]
escalation free contract
[473]
Supply of material by client. So what are the material supplied by the plant? So we mentioned here and what will be the wastage consumer?
[481]
Consideration this is mentioned in this cloth and last but not the least
[485]
reduction money and sequel to deposit which I explained earlier at the time of
[490]
defect liability period so this retention amount is withheld with the
[495]
client for the
[498]
rectification of the work if contract have not rectify the work during the difficulty period so by this security amount that