馃攳
20-- The Concept of Equivalent Units of Production - YouTube
Channel: unknown
[0]
[Music]
[5]
I'm Larry Walter this is principles of
[8]
accounting dot-com chapter 20 and we're
[11]
looking at process costing and
[12]
activity-based costing in this specific
[15]
module we're going to consider the
[16]
concepts of equivalent units in the
[18]
previous module we talked about the
[20]
general characteristics of process
[22]
costing now we're going to get into the
[24]
nuts and bolts of process costing and
[26]
that begins by understanding the concept
[28]
of equivalent units and how we're going
[30]
to determine the cost per equivalent
[32]
unit and so an equivalent unit is an
[35]
abstract concept it's simply a physical
[37]
unit expressed in terms of a finished
[39]
unit for example if we have 10 units and
[41]
process that are 30% complete we can
[45]
simply say that that process relates to
[47]
our equates to 3 equivalent units of
[50]
output 30% of 10 none of the 10 units is
[53]
complete it's simply that the equivalent
[55]
amount of work necessary to complete 3
[57]
units is said to be performed now
[60]
recognize that equivalent units is not
[63]
necessarily the same across all factors
[65]
of production we have material labor and
[67]
overhead for example we might be only
[69]
80% complete with respect to materials
[72]
and only 60% complete with respect to
[74]
labor and overhead so we would have more
[77]
equivalent units of material in process
[79]
than we would equivalent units of
[80]
conversion costs in process and that's
[82]
perfectly fine perfectly logical but it
[85]
will cause us to adapt our calculations
[89]
to reflect that fact
[90]
of course if overhead is applied based
[92]
on the labor of the process is
[93]
simplified as I've assumed here that if
[96]
we're 60 percent complete with respect
[98]
to labor I've also assumed were 60
[100]
percent complete with respect to
[101]
overhead as labor is the application
[103]
base I've assumed in this example now
[106]
the textbook has an example for novaro
[108]
steel and I'm simply following along
[110]
with that illustration the first stage
[111]
in the verrell's production process is
[114]
the melting department and so Navaro I'm
[116]
assuming started the month with 300
[118]
thousand tons of ore in process during
[121]
the month they added an additional
[122]
600,000 tons in the process thus there's
[126]
900 thousand total units that must be
[128]
reconciled or accounted for
[130]
or I'm assuming 650,000 tons were
[133]
transferred on to the next department
[135]
leaving 250,000 in process at the end so
[138]
we can then look at a unit
[140]
reconciliation and this is the beginning
[142]
point to get our arms around the total
[144]
units that are involved in a particular
[147]
process during a particular period and
[149]
so here are the 900,000 tons that we
[151]
need to explain or reconcile or
[154]
determine the disposition of and we know
[157]
that 650,000 tons were transferred out
[159]
and we verified that 250 we're still in
[161]
process at the end of the month in the
[164]
Melting department so that nine hundred
[165]
thousand and nine hundred thousand that
[167]
reconciliation is highly important of
[170]
course it's possible that the total
[172]
units that went in are not equal to the
[173]
units that went out and remain in
[176]
process we may have evaporation or
[178]
spillage or spoilage or waste or scrap
[180]
of some type if that's normal in the
[183]
production process we allow for that in
[185]
other words in our reconciliation we
[187]
would say well we had 600,000 units
[189]
transferred out 250,000 units still in
[192]
process and 50,000 simply evaporated if
[195]
that were the case we would then take
[197]
the total cost and assign it to the good
[199]
units we're not going to assign cost to
[201]
the normal spoilage the cost that
[203]
relates to that simply gets pulled in
[205]
and applied to the units that are
[207]
actually making their way toward
[208]
finished goods now that's for normal
[211]
spoilage abnormal spoilage or excessive
[213]
waste we might go ahead and track cost
[215]
for those units assigned cost to those
[217]
units and reconcile those amounts as
[220]
lost components and report that as such
[222]
in the income statement now as with any
[225]
inventory method and process costing is
[227]
an inventory costing method we need to
[229]
adopt a cost flow assumption I'm going
[231]
to use weighted average illustration in
[233]
this particular case we could do this in
[236]
an alternative process called FIFO
[238]
costing we need to do one way or the
[240]
other and so let's look at this under
[241]
the average costing method and we're
[243]
going to average together the cost
[244]
associated with beginning inventory and
[247]
current period production and so the
[250]
left-hand side of the slide this is the
[252]
schedule we just developed the
[253]
reconciliation of the units that existed
[256]
we've already seen we've explained how
[258]
the 900,000 units went into production
[260]
and where they ended
[262]
the end of the month also I'm adding an
[264]
additional fact here the ending work in
[266]
process status the materials a 50%
[269]
injected into the process and the
[272]
conversion cost labor and overhead is 40
[274]
percent complete so we're actually
[276]
complete with respect to the ending work
[278]
in process and here's how this works out
[280]
the 650,000 units that were completed
[284]
and transferred to the next department
[285]
they're 100% complete with respect to
[287]
material labor and overhead but the
[289]
ending work in process 250,000 tonnes
[292]
being 50 percent complete with respect
[294]
to materials gives us the 125,000
[297]
equivalent units of materials and 40
[300]
percent of the 250 thousand gives us the
[302]
100 thousand units of conversion cost
[305]
that means then for the month our
[308]
equivalent units calculations need to be
[310]
based upon 775 thousand tons of direct
[314]
materials and conversion relates to the
[317]
labor and overhead necessarily convert
[319]
seven hundred and fifty thousand
[320]
equivalent units of finished process and
[324]
that information is vital as we go
[327]
forward calculating the cost per
[329]
equivalent unit and so another schedule
[331]
here in some more facts our beginning
[333]
working process contained two million
[335]
one hundred twenty two thousand five
[337]
hundred and then an additional seven
[339]
million 365 was added into process
[342]
during the month distributed between
[344]
material labor and overhead so we've got
[346]
a total cost to account for the actual
[348]
cost signs nine million four eighty
[349]
seven five hundred broken down between
[352]
material labor and overhead and now
[354]
here's where the equivalent units comes
[355]
into play we'll divide each of those
[357]
cost pools by the equivalent units
[359]
related to that cost pool to come up
[361]
with the cost per equivalent unit very
[364]
simply our materials average cost is
[367]
nine dollars a ton our conversion cost
[369]
average is 335 a turn our total cost for
[372]
one complete equivalent unit of output
[374]
is twelve dollars and 35 cents and so
[377]
this is the calculation of the cost per
[379]
equivalent unit these numbers will
[381]
become essential and vital as we go
[383]
forward and in fact we'll incorporate
[385]
this part of this schedule into our
[387]
final cost of production report that
[389]
we'll see in a subsequent module
Most Recent Videos:
You can go back to the homepage right here: Homepage





