Supreme Court on Binding Nature of a Letter of Intent - YouTube

Channel: Suyash Verma | Legal Talks by Desikanoon

[0]
hi everyone welcome to legal talks by
[2]
desi kanoon i am suyash and i am excited
[5]
to have started this show
[7]
on today's show we will talk about the
[9]
case of southeastern coal fields limited
[12]
and others versus escu mars associates
[14]
akm
[15]
joint venture in this case the court
[18]
discussed whether a letter of
[20]
intent executed between the parties to
[22]
enter into a contract
[24]
could be construed as binding or not
[27]
the brief facts of the case are that a
[29]
works contract relating to
[31]
excavation and mining was sought to be
[33]
entered into between the appellant and
[35]
the respondent
[36]
in furtherance to which a letter of
[38]
intent dated
[40]
5th of october 2009 was executed between
[43]
the parties
[44]
subsequently on 28th of october 2009
[48]
the respondent got all its equipments
[50]
and machineries at the worksite
[53]
and commenced its work however on 5th of
[56]
december 2009
[58]
while performing the work the
[60]
truck-mounted
[61]
drill machine of the respondent suffered
[63]
a major breakdown
[65]
and the work got suspended for reasons
[68]
beyond the control of the respondent
[70]
the respondent sought three months time
[72]
for purchase of new machines
[74]
but on 9th of december 2009 a show-cause
[77]
notice was issued by the appellant
[80]
to the respondent alleging reach of
[82]
contract
[83]
thereafter multiple correspondences and
[85]
notices were exchanged between the
[87]
parties
[88]
and on 16th of july 2010 the appellant
[91]
issued a notice to the respondent
[94]
seeking compensation of around rupees 78
[97]
lakhs
[98]
being the differential in the contract
[99]
value between the respondent
[101]
and the new contractor this
[104]
notice-seeking compensation was
[105]
challenged by the respondent before the
[108]
high court of chhattisgard
[109]
and the high court of chhattisgard
[111]
passed the impugned order dated 7th of
[113]
november 2012
[115]
holding that there was no valid contract
[118]
between the parties
[120]
and only for feature of bid security was
[122]
permitted
[123]
but the additional amount in a word of
[126]
contract to another contractor as
[128]
compared to the respondent
[129]
was held to be not recoverable
[133]
hence the appellant appealed against the
[135]
order dated 7th of november 2012
[138]
before the honorable supreme court
[141]
firstly the court observed that
[143]
the letter of intent between the parties
[145]
merely indicated the intention
[147]
to enter into a contract with each other
[149]
at a future point of time
[152]
and a letter of intent could be
[153]
construed as binding
[155]
only if such an unambiguous intention is
[158]
evident from its terms
[160]
secondly the court noted that in the
[163]
present case the period of execution of
[165]
contract was one year
[167]
whereas the respondent worked only for a
[170]
month and no money was paid for the work
[172]
already done according to the court the
[175]
respondent clearly failed to comply with
[177]
the obligations stipulated under the
[179]
letter of intent
[181]
however neither any performance security
[184]
deposit was furnished by the respondent
[187]
nor any formal work order was issued by
[189]
the appellant in favor of the respondent
[192]
so whether there exists a valid contract
[194]
or not in the present case remains
[196]
doubtful thirdly
[198]
the court produced clause 29.2 of the
[201]
nit
[202]
the notice inviting tender that
[204]
stipulated that
[206]
the notification of award will
[207]
constitute the formation of the contract
[210]
subject only to furnishing of the
[212]
performance security or security deposit
[216]
the court also produced clause 9 of the
[218]
nit
[219]
that explained what constitutes the
[221]
contract
[223]
according to clause 9 the contract
[225]
includes the nit
[226]
the acceptance of the tender the formal
[229]
agreement to be executed between the
[231]
parties
[232]
post contractor furnishing all the
[234]
documents and
[235]
the bid security amount thus only a
[238]
letter of intent is not sufficient to be
[240]
relied upon
[242]
and the contract must be wholly executed
[245]
in order to allege its breach
[247]
therefore upon cumulative consideration
[250]
the quote was of the view that
[251]
the high court of chhattisgard was right
[254]
in holding that
[255]
the only thing that the appellant can do
[257]
is to forfeit the bid security amount
[260]
and refund the balance amount to the
[262]
respondent
[263]
any recovery of the differential value
[266]
of the so called contract awarded to the
[268]
respondent
[269]
and to the new contractor was held to be
[272]
not recoverable
[273]
hence the appeal preferred by the
[275]
appellant was dismissed
[277]
those were the observations by the court
[279]
so what are my
[280]
concluding remarks i concur with the
[283]
interpretation of the honorable supreme
[285]
court
[286]
that only in cases where a letter of
[288]
intent mentions in
[289]
unambiguous terms that it would be
[291]
binding
[292]
can it be contended that there has been
[295]
a breach of contract
[297]
a letter of intent is what it is it
[300]
merely signifies the intent of the
[302]
parties
[302]
to enter into an agreement and it is
[305]
akin to an acceptance of an invitation
[307]
to offer and
[308]
not the offer itself hence i hope you
[311]
enjoyed listening to this show
[313]
thank you for listening please do not
[315]
forget to like and subscribe us
[318]
and if you have any comments please make
[320]
them in the comments
[321]
section see you next time till then stay
[324]
tuned