Percentage of Completion Method (Definition) | 3 Methods to Calculate it - YouTube

Channel: WallStreetMojo

[10]
hello everyone hi welcome to the channel of WallStreetmojo
[14]
watch the video till the end also if you are new to this channel then you can
[18]
subscribe us by clicking the bell icon today we have a topic with us as
[22]
percentage of completion method well in this topic we will try and incorporate
[26]
all the methodology part of how the method is used it is used for every
[31]
recognition initially it was recorded in the construction contracts that was es7
[36]
now it has a separate recognition in es9 so what is the percentage of POC a
[43]
method percentage of completion method see percentage of completion method is
[46]
basically an accounting method for recognition not only of revenue but also
[52]
of the expenses for the long term projects which span over more than one
[58]
accounting year so in this method revenues recognized on what we call as
[61]
yearly basis as a percentage of the work that is completed during the year so
[65]
revenue for the given year is calculated as revenue is equal to percentage of
[71]
work that has been completed in the given period into the total contract
[77]
value okay so here the biggest challenge is to calculate the percentage of the
[81]
work that has been completed now how to calculate the percentage of the work
[85]
calculate work that has been completed that is our second point of discussion
[90]
how to calculate the percentage of the work that has been completed well to
[98]
estimate the progress of the work or the completion percentages
[101]
companies can use either of the three methods the first one goes as the cost
[105]
method to calculate the percentage completion now in case of the huge
[113]
projects the total cost which will be incurred on the projects is estimated at
[117]
the start of the project and itself so that a new company can accordingly go to
[120]
fee for the same so this cost can be taken as the basis for the calculating
[127]
the percentage of the completion method as it is you know assume that the
[132]
revenue will go hand-in-hand with cost incurred so the determine all
[135]
completed you can use the following formula
[138]
something like there is the percentage of the work completed is equal to your
[146]
total expenses okay that is incurred on the project till clause to the
[154]
close of the accounting period that will be divided by the total estimated cost
[160]
of the contract okay so the above formula gives the cumulative percentage
[165]
of the work completed on until the close of the accounting period and from this
[168]
you need to subtract you need to do what you need to you need to subtract the
[172]
percentage of the work that has been completed up to the last accounting
[177]
period to arrive at the percentage is the Welcome written in current accounting
[180]
year no issues this is going little bit about the headline but no shoes we have
[185]
an example to hedge the condition see percentage of complete completion
[191]
methods example see let's say a company named roads and bridges have worn a
[196]
contract for a construction of the foot over bridges near crowded railway
[199]
stations it is estimated that the total cost for the projects will be let's say
[203]
a 1 million and this policy of the company is to add a margin of 20%
[209]
on its cost estimate so the finalized quotation for the project which is
[213]
agreed by both parties is let's say 1 million plus 1. x 1.2
[220]
- that's gonna be 1,00,000 and 1,20,000 that's 1.2 million so it is
[225]
estimated the company will be able to finish its project in the 3 years of
[228]
times let's say that and the company has in cost during the life of the project
[232]
some somewhere like this year 1 let's say 1,00,000 year 2 is standing at
[241]
3,50,000 year 3 is standing at 4,75,000 you're standing at let's say
[251]
1,00,000 so these are all the couple of details that are there so on the basis
[255]
of the following cost method of percentage completion
[258]
revenue can be recognized somewhat like this now I'll form a table here 1 2 3 &
[265]
4 the cost that has been in here that is 1,00,000 and 3,50,000 we have to
[271]
3,50,000 and 4,75,000 the last one is 1,00,000 ok cumulative percentage
[281]
completion that's what we are supposed to indicate here so cumulative
[285]
percentage will be based on the amount that has been used so this this amount
[290]
first will have to accumulate 1,00,000 here
[293]
1,00,000+3,50,000 and then it goes around 8,25,000 so that's 475+
[299]
3,50,000 and 5,75,000 that's the final amount the 1,00,000 or
[303]
4,50,000 ,4,75,000+ 4,79,000 that 24 this 1,00,000 + 9,25,000 so
[309]
10,25000 now we will see the percentage part how much it is completed
[313]
of the so the percentage is calculated the cumulative percentage of the
[324]
completed part that is what we are supposed to calculate and year on year
[329]
percentage so the percentage will be calculated as you know the total the
[333]
cumulative value of completion divided by the total cost that has been involved
[337]
and make this as constant completely constant 10,25000
[342]
and you will get the details for the percentage the cumulative percentage of
[348]
completion now let's see that year on year percentage why and why percentage
[352]
calculation so that's gonna be 10% for the first year there's gonna
[356]
be no change we have 44 - 25 so 34% here 95 - 44 so 90%
[365]
minus 34 that's 56 and 100 minus 56 that's 44 so this is Y and Y
[371]
calculation that has been determined so this is how the calculation is done it's
[375]
a long long long process that's that's that how it has been worked out the main
[379]
important part that I want to take you to is not only this part but there are
[383]
some of the prerequisite for calculating this method the prerequisite that for
[389]
the percentage is a completion method that goes is that you know one of the basic
[392]
principle of the accounting of prudence has been followed here and this
[395]
accounting principle requires that you know certain degree of should be
[397]
exercised while recording the revenue the books of accounts so keeping this Prince
[401]
mine use the percentage of the completion method should be used booking the
[405]
revenues for booking revenue in the books of account only when the following
[410]
can be a short like unknown first collections with regards to the
[413]
contracts is assured and to ensure companies ask to bank guarantees and
[418]
performing guarantees from the debtors they can also check for the
[420]
credit worthiness of the company before entering into contract the company can
[423]
fairly determine the what we call as progress of the work done on the
[427]
contract if this is important because the revenue is directly related to the
[430]
progress now this are the couple of things that should be taken in the mind
[433]
before putting down all the numbers well on the part of the journal entries the
[438]
revenue is recognized under the percentage completion method is not built to the
[442]
customer and revenue recognition in this case should be routed a different
[445]
account called the unbilled contract receivable account by this it goes
[450]
around and the ocm method is not only used in the revenue recognition but
[456]
mostly it is used in the construction contract method where there is
[460]
escalation of the revenues relation of and distribution or based on the
[466]
completion of the work done work certified and completion of work
[474]
uncertified so with this all you know it it is very important to understand that
[479]
POCM is used highly used in the accounting accounting scenarios in the
[482]
accounting language so that's it for this particular topic if you have
[486]
learned and enjoyed watching this video please like and comment on this video
[491]
and subscribe to our channel for the latest updates thank you everyone
[495]
Cheers