馃攳
Project Scheduling 2 -Calculating variance and probabilities -PERT/CPM - YouTube
Channel: Joshua Emmanuel
[0]
Hello there!
In this video on project scheduling, I will
[4]
be calculating expected times and variances
for uncertain activity times. I鈥檒l also
[9]
be calculating probabilities of completing
a project at specified times. And lastly,
[15]
I鈥檒l be calculating the completion time
of a project at a stated probability.
[21]
Here we have a table showing activity predecessors
and their uncertain time estimates. Optimistic,
[28]
Most Likely, and Pessimistic times are represented
by a, m, and b respectively.
[34]
To calculate the expected time t we apply
this formula: t = a plus 4m plus b over 6.
[42]
So the expected time for A is calculated as
4 + 4 times 6 + 14, divided by 6. And that
[50]
gives 7.
We do the same for Activity B, C, D, E, F,
[58]
and G.
And using these expected activity times and
[61]
predecessors, I completed the project network
from scratch in an earlier video. You will
[66]
find the link provided in description.
The critical path is BDEF and the project
[74]
completion time is 32 weeks.
Note that the project completion time can
[80]
also be found by adding up the expected activity
times for the critical activities.
[85]
Now, the formula for calculating the variance
for each activity is b minus a divided by
[90]
6 squared.
Just like the project completion time can
[95]
be found by adding up the expected activity
times for critical activities, the project
[100]
variance is also found by adding up the variances
for critical activities. So we only need to
[106]
calculate the variances for the critical activities.
Thus, for B, the variance is 2.78, for D,
[113]
1.78, for E, 2.78 and for F, the variance
is 1.
[122]
And adding these, we have the project variance
of 8.33. Then taking the square root we have
[128]
the project standard deviation of 2.8867.
Although the uncertain time estimates are
[135]
beta distributed, we can approximate the project
completion time by a normal distribution.
[141]
In this case, with mean equals 32 and standard
deviation 2.8867.
[148]
So we can apply the z formula to answer these
questions.
[152]
First, we find the probability that the project
will be completed within 35 weeks. That is,
[158]
x equals 35 and that gives z = 1.04. And looking
it up in tables we have a less-than area of
[167]
.8508.
For x greater than 31, we have z greater than
[173]
-0.35. The area less than -0.35 is 0.3632.
And subtracting it from 1 we obtain the more-than
[183]
area of 0.6368.
Between 31 and 35, we find the area between
[190]
their z values of -0.35 and 1.04 by subtracting
the smaller area from the larger one. And
[198]
that gives 0.4876.
For d), less than 31 or more than 35 is the
[205]
complement of our result in c). So we just
subtract the result from 1 to obtain 0.5124.
[212]
Next, if we want a 90% probability of completing
the project on time, we do a reverse lookup
[220]
for a less-than area of 0.90. That will correspond
to a z-score of 1.28.
[227]
And substituting that into the z formula we
obtain a completion time of about 35.7. That
[234]
is, the project should begin about 36 weeks
earlier in order to be completed on time with
[240]
a 90% probability.
And that鈥檚 it for this video.
[245]
Thanks for watching.
Most Recent Videos:
You can go back to the homepage right here: Homepage





